Umarahat Pump Canal Phase - I Medium Irrigation Project JI01920

« Go Back

#AttributeValue
1Irrigation Project Name Umarahat Pump Canal Phase - I Medium Irrigation Project
2Irrigation Project Name Alias
3Purpose Irrigation
4Type Medium
5Engineering Type Lift
6Status Completed
7State Uttar Pradesh
8Districts Benefited Kanpur Dehat
9Basin Ganga
10River Yamuna
11Project Sharing None
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan V-Plan
15Completed in 5 Year Plan VII-Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 1977
18Approved Cost (Rs. in cr) .78
19Actual Cost (Rs. in cr) 3.93
20Culturable Command Area (CCA) (th ha) 4.86
21Ultimate Irrigation Potential (UIP) (th ha) 3.96
22Potential Created (PC) (th ha) 3.96
23Project Covered under ERM Scheme No
24Project Covered under CADA Scheme No
25Project Covered under AIBP Scheme No
26Studies Conducted
27Project Covered under Tribal Sub-Plan
28Project Covered under Drought Prone Area Programme (DPAP)
29Remarks
#NameType
1Umarahat Lift StationLift