Ukai Major Irrigation Project JI01035

« Go Back

#↓Attribute↓Value↓
1Irrigation Project Name Ukai Major Irrigation Project
2Irrigation Project Name Alias
3Purpose Irrigation
4Type Major
5Engineering Type Diversion, Storage
6Status Completed
7State Gujarat
8Districts Benefited Valsad,Navsari,Surat,Bharuch,Tapi
9Basin Narmada, Tapi, West flowing rivers from Tapi to Tadri
10River Tapi
11Project Sharing None
12Intercountry None
13Interbasin Yes
14Work Started in 5 Year Plan III-Plan
15Completed in 5 Year Plan V-Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 1961
18Approved Cost (Rs. in cr) 58.21
19Actual Cost (Rs. in cr) 136.43
20Culturable Command Area (CCA) (th ha) 127.48
21Ultimate Irrigation Potential (UIP) (th ha) 131
22Potential Created (PC) (th ha) 131
23Project Covered under ERM Scheme Yes
24Project Covered under CADA Scheme Yes
25Project Covered under AIBP Scheme No
26Studies Conducted
27Project Covered under Tribal Sub-Plan Yes
28Project Covered under Drought Prone Area Programme (DPAP) Yes
29Remarks Ukai is phase - II project of kakrapar Ukai
project. They are now combined projects as
kakrapar barrage gets regulated releases from Ukai
dam
#↓Name↓Type↓
1Kakrapar BarrageBarrage/ Weir/ Anicut (BWA)
2Ukai DamDam


Print/export
QR Code
QR Code ukai_major_irrigation_project_ji01035 (generated for current page)