Tillari Major Irrigation Project Maharashtra JI03566

« Go Back

#AttributeValue
1Irrigation Project Name Tillari Major Irrigation Project_Maharashtra
2Irrigation Project Name Alias
3Purpose Irrigation
4Type Major
5Engineering Type Diversion, Storage
6Status Ongoing
7State Maharashtra
8Districts Benefited Kolhapur,Sindhudurg,North Goa
9Basin West flowing rivers from Tapi to Tadri
10River Tillari,Kharani Nalla
11Project Sharing Interstate
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan AP (1978-80)
15Completed in 5 Year Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 2000
18Approved Cost (Rs. in cr) 76.19
19Actual Cost (Rs. in cr)
20Culturable Command Area (CCA) (th ha) 6.68
21Ultimate Irrigation Potential (UIP) (th ha) 9.68
22Potential Created (PC) (th ha)
23Project Covered under ERM Scheme No
24Project Covered under CADA Scheme No
25Project Covered under AIBP Scheme Yes
26Studies Conducted
27Project Covered under Tribal Sub-Plan
28Project Covered under Drought Prone Area Programme (DPAP)
29Remarks


Print/export
QR Code
QR Code tillari_major_irrigation_project_maharashtra_ji03566 (generated for current page)