#AttributeValue
1Irrigation Project Name Sirhind Feeder Major Irrigation Project
2Irrigation Project Name Alias
3Purpose Irrigation
4Type Major
5Engineering Type Diversion
6Status Completed
7State Punjab
8Districts Benefited Faridkot,Firozpur,Ganganagar,Sirsa,Muktsar
9Basin Indus up to International Border
10River Satluj
11Project Sharing None
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan I-Plan
15Completed in 5 Year Plan II-Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 1956
18Approved Cost (Rs. in cr) 3.39
19Actual Cost (Rs. in cr) 6.71
20Culturable Command Area (CCA) (th ha) 360
21Ultimate Irrigation Potential (UIP) (th ha)
22Potential Created (PC) (th ha)
23Project Covered under ERM Scheme No
24Project Covered under CADA Scheme Yes
25Project Covered under AIBP Scheme No
26Studies Conducted
27Project Covered under Tribal Sub-Plan
28Project Covered under Drought Prone Area Programme (DPAP)
29Remarks Offtake from Ferozpur feeder
#NameType
1Harike BarrageBarrage/ Weir/ Anicut (BWA)