Sidhatha Medium Irrigation Project JI01706

« Go Back

#AttributeValue
1Irrigation Project Name Sidhatha Medium Irrigation Project
2Irrigation Project Name Alias
3Purpose Irrigation
4Type Medium
5Engineering Type Diversion
6Status Ongoing
7State Himachal Pradesh
8Districts Benefited Kangra
9Basin Indus up to International Border
10River Dehar
11Project Sharing None
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan IX-Plan
15Completed in 5 Year Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 2000
18Approved Cost (Rs. in cr) 33.62
19Actual Cost (Rs. in cr)
20Culturable Command Area (CCA) (th ha) 3.15
21Ultimate Irrigation Potential (UIP) (th ha) 5.35
22Potential Created (PC) (th ha)
23Project Covered under ERM Scheme No
24Project Covered under CADA Scheme No
25Project Covered under AIBP Scheme Yes
26Studies Conducted
27Project Covered under Tribal Sub-Plan No
28Project Covered under Drought Prone Area Programme (DPAP)
29Remarks
#NameType
1Sidhatha WeirBarrage/ Weir/ Anicut (BWA)

Project in Brief

Sidhatha Medium Irrigation Project with an initial estimated cost of Rs 33.62 crore (1996-97 Price level) is located in Jawali Tehsil of Kangra district, Himachal Pradesh. The Project was started in the year 1997-98 to provide irrigation facility in Jawali Area covering a CCA of 3150 ha with an ultimate Irrigation potential of 5350ha. The estimated cost of the project was revised in year 2007 to Rs 66.35 crore (2006 price level) and was approved by TAC & Planning Commission, GOI in year 2007. In August 2010, the cost of the project is re-revised to Rs 95.29 crore which is approved by P.C in April-2011. The various components of the projects are as under:


i)Head works-Weir

Project envisages diversion of water of Dehar stream, a tributary of the river Beas, to irrigate 3150 ha of CCA by constructing a diversion weir near Village Anuhi. The water from weir will be carried to fields through a 13.771 km long main canal water conductor system.

ii)Main Canal (water conductor system)

13.771 km long Main Canal water conductor system is proposed on right bank of Dehar stream with maximum discharging capacity of canal at head of 3.26 cumecs (as against the water requirement of the project of 2.61 Cumecs) to irrigate 3005 ha of CCA.

iii) Distributaries

Three numbers lined distributaries network namely D-1, D-2 and D-3 of total 11.100 km length have been proposed from main canal in the project. Length of distributaries D-1, D-2 and D-3 is 5.6 km, 3.2 km and 2.3 km respectively.

iv)Lift Schemes

7 numbers of lift schemes with a total capacity of 1861 BHP have been proposed to irrigate 773 ha CCA at higher elevations where irrigation is not possible by gravity flow. One lift scheme is situated on left bank of the Dehar stream to irrigate an area of 145 ha and 6 lift schemes are situated on right bank to irrigate 628 ha of CCA. The water for one number left bank Lift Irrigation scheme is to be lifted from head works and for remaining 6 LIS on the right bank, water will be lifted from different locations from Main canal by installing pumping machinery and rising mains.

The project is brought under AIBP since 2000-01 and so far irrigation potential of 823.39 hectare is created.