Sathnur Reservoir Irrigation Project JI02593

« Go Back

#↓Attribute↓Value↓
1Irrigation Project Name Sathnur Reservoir Irrigation Project
2Irrigation Project Name Alias
3Purpose Irrigation
4Type Medium
5Engineering Type Storage
6Status Completed
7State Tamil Nadu
8Districts Benefited Tiruvannamalai,Viluppuram
9Basin East flowing rivers between Pennar and Kanyakumari
10River Ponniar
11Project Sharing None
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan I-Plan
15Completed in 5 Year Plan II-Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 1954
18Approved Cost (Rs. in cr) 2.63
19Actual Cost (Rs. in cr) 2.82
20Culturable Command Area (CCA) (th ha) 7.68
21Ultimate Irrigation Potential (UIP) (th ha) 7.68
22Potential Created (PC) (th ha) 7.68
23Project Covered under ERM Scheme Yes
24Project Covered under CADA Scheme Yes
25Project Covered under AIBP Scheme No
26Studies Conducted
27Project Covered under Tribal Sub-Plan
28Project Covered under Drought Prone Area Programme (DPAP)
29Remarks
#↓Name↓Type↓
1Sathanur AnnicutBarrage/ Weir/ Anicut (BWA)
2Sathanur DamDam


Print/export
QR Code
QR Code sathnur_reservoir_irrigation_project_ji02593 (generated for current page)