1 | Irrigation Project Name | Saryu Nahar Pariyojana Major Irrigation Project |
2 | Irrigation Project Name Alias | |
3 | Purpose | Irrigation |
4 | Type | Major |
5 | Engineering Type | Diversion |
6 | Status | Ongoing |
7 | State | Uttar Pradesh |
8 | Districts Benefited | Gorakhpur,Sant Kabir Nagar,Balrampur,Siddharth_PARATABLE_INS_Nagar,Bahraich,Sitapur,Shrawasti,Maharajganj,Faizabad,Deoria,Basti,Bara_PARATABLE_INS_Banki,Azamgarh,Ambedkar Nagar,Gonda |
9 | Basin | Ganga |
10 | River | Saryu, Rapti |
11 | Project Sharing | None |
12 | Intercountry | None |
13 | Interbasin | No |
14 | Work Started in 5 Year Plan | V-Plan |
15 | Completed in 5 Year Plan | |
16 | Project Approval Status | Planning Commission |
17 | Year of Approval by Planning Commission | 1998 |
18 | Approved Cost (Rs. in cr) | 1579.31 |
19 | Actual Cost (Rs. in cr) | |
20 | Culturable Command Area (CCA) (th ha) | 1200 |
21 | Ultimate Irrigation Potential (UIP) (th ha) | 1404 |
22 | Potential Created (PC) (th ha) | |
23 | Project Covered under ERM Scheme | No |
24 | Project Covered under CADA Scheme | Yes |
25 | Project Covered under AIBP Scheme | Yes |
26 | Studies Conducted | |
27 | Project Covered under Tribal Sub-Plan | No |
28 | Project Covered under Drought Prone Area Programme (DPAP) | |