#AttributeValue
1Irrigation Project Name Ralivagu Medium Irrigation Project
2Irrigation Project Name Alias Ralivagu (Mukakala)
3Purpose Irrigation
4Type Medium
5Engineering Type Diversion
6Status Completed
7State Telangana
8Districts Benefited Adilabad,Karimnagar
9Basin Godavari
10River Godavari
11Project Sharing None
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan X-Plan
15Completed in 5 Year Plan XII-Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 2006
18Approved Cost (Rs. in cr) 33.3
19Actual Cost (Rs. in cr) 47.9
20Culturable Command Area (CCA) (th ha) 2.43
21Ultimate Irrigation Potential (UIP) (th ha) 2.43
22Potential Created (PC) (th ha) 2.43
23Project Covered under ERM Scheme No
24Project Covered under CADA Scheme No
25Project Covered under AIBP Scheme Yes
26Studies Conducted
27Project Covered under Tribal Sub-Plan
28Project Covered under Drought Prone Area Programme (DPAP)
29Remarks
#NameType
1Ralivagu WeirBarrage/ Weir/ Anicut (BWA)

The Ralivagu Project is situated near Mulkala village in Mancherial mandal of Adilabad district of Andhra Pradesh. The project comprises of an earthen dam of length 2.15 km including Ogee Weir of length 180.0 m for a design discharge of 940.69 cumec, left and right bank canals to create an irrigation potential of 2,428 ha with lengths of 5.20 km and 4.24 km respectively.

The project was approved by the Planning Commission, Water Resource Division in the year 2006 for Rs.33.30 cr vide Planning Commission letter No.20(1)/2006-WR dt. 27.6.2006. The latest estimated cost of the project is Rs.49.71 cr. The project was started during the year 2005 and is likely to be completed in the year 2010-11.