Pullambadi Canal Medium Irrigation Project JI02570

« Go Back

#AttributeValue
1Irrigation Project Name Pullambadi Canal Medium Irrigation Project
2Irrigation Project Name Alias
3Purpose Irrigation
4Type Medium
5Engineering Type Diversion, Storage
6Status Completed
7State Tamil Nadu
8Districts Benefited Ariyalur,Tiruchirappalli
9Basin Cauvery
10River Cauvery
11Project Sharing None
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan II-Plan
15Completed in 5 Year Plan II-Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 1957
18Approved Cost (Rs. in cr) 2.63
19Actual Cost (Rs. in cr) 2.06
20Culturable Command Area (CCA) (th ha) 8.94
21Ultimate Irrigation Potential (UIP) (th ha) 8.94
22Potential Created (PC) (th ha) 8.94
23Project Covered under ERM Scheme No
24Project Covered under CADA Scheme No
25Project Covered under AIBP Scheme No
26Studies Conducted
27Project Covered under Tribal Sub-Plan
28Project Covered under Drought Prone Area Programme (DPAP)
29Remarks
#NameType
1Pullambadi Head SluiceBarrage/ Weir/ Anicut (BWA)
2Upper AnicutBarrage/ Weir/ Anicut (BWA)


Print/export