Pulivendula Branch Canal Major Irrigation Project JI00003

« Go Back

#↓Attribute↓Value↓
1Irrigation Project Name Pulivendula Branch Canal Major Irrigation Project
2Irrigation Project Name Alias Chitravathi Balancing Reservoir
3Purpose Irrigation
4Type Major
5Engineering Type Storage
6Status Completed
7State Andhra Pradesh
8Districts Benefited Anantapur,Y.s.r.
9Basin Pennar
10River Chitravathi,Pennar
11Project Sharing None
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan IV-Plan
15Completed in 5 Year Plan XII-Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 1972
18Approved Cost (Rs. in cr) 2.98
19Actual Cost (Rs. in cr) 197.15
20Culturable Command Area (CCA) (th ha) 24.7
21Ultimate Irrigation Potential (UIP) (th ha) 24.28
22Potential Created (PC) (th ha) 24.28
23Project Covered under ERM Scheme No
24Project Covered under CADA Scheme No
25Project Covered under AIBP Scheme No
26Studies Conducted
27Project Covered under Tribal Sub-Plan
28Project Covered under Drought Prone Area Programme (DPAP)
29Remarks get suplies from TBHLC-II
#↓Name↓Type↓
1Chitravathi DamDam
2Goddumari AnicutBarrage/ Weir/ Anicut (BWA)
3Lift-1 PBCLift
4Lift-2 PBCLift
5Midpennar Stage-I/Mid-Pennar DamDam


Print/export
QR Code
QR Code pulivendula_branch_canal_major_irrigation_project_ji00003 (generated for current page)