Madan Medium Irrigation Project JI00549

« Go Back

#AttributeValue
1Irrigation Project Name Madan Medium Irrigation Project
2Irrigation Project Name Alias
3Purpose Irrigation
4Type Medium
5Engineering Type Diversion, Storage
6Status Completed
7State Maharashtra
8Districts Benefited Wardha
9Basin Godavari
10River Madan Nalla
11Project Sharing None
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan VII-Plan
15Completed in 5 Year Plan XI-Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 1981
18Approved Cost (Rs. in cr) 3.08
19Actual Cost (Rs. in cr)
20Culturable Command Area (CCA) (th ha) 4.06
21Ultimate Irrigation Potential (UIP) (th ha) 3.28
22Potential Created (PC) (th ha) 3.28
23Project Covered under ERM Scheme No
24Project Covered under CADA Scheme No
25Project Covered under AIBP Scheme Yes
26Studies Conducted
27Project Covered under Tribal Sub-Plan No
28Project Covered under Drought Prone Area Programme (DPAP)
29Remarks
#NameType
1Madan DamDam
2Madan WeirBarrage/ Weir/ Anicut (BWA)

Brief Description

The Madan Tank Medium Irrigation Project is constructed in the Godavari Basin in Wardha district of Maharashtra State. The project components are as under.

  • 1230 m long earth dam with maximum height of 26.55 m and 140 m long waste weir across Madan Nallah to pass maximum flood of 662.50 m3/s near village Madan in Arvi tahsil.
  • 3488 m long and 12.64 m high Pick-up weir with 157.80 m long central ogee-type spillway 12 km d/s of the main dam near Wadgaon village in Seloo Taluka. The central spillway is designed to pass maximum flood of 1036.40 m3/s.
  • Two main canals i.e. the Left Bank Canal (LBC) with the designed discharge of 2.02 m3/s and the Right Bank Canal (RBC) with the designed discharge of 1.91 m3/s of length 13.17 km and 11.52 km respectively taking off from the Pick-up weir to irrigate an area of 2535 ha (ICA) in a CCA of 4056 ha. The ultimate irrigation potential of the project is 3270 ha.

The Planning Commission approved the project in 1981 for Rs. 3.08 crore. The construction of the project started in 1979 but the work was held up from 1979 to 1996 for want of forest clearance. The work resumed in 1997. Subsequently the project was brought under AIBP during 2005-06 and the project is completed during 2008-09 and full potential is developed. The latest estimated cost of the project at 2004-05 price level is Rs. 88.09 crore.