Kurnool Cuddapah Canal Major Irrigation Project JI03603
# | Attribute | Value |
---|---|---|
1 | Irrigation Project Name | Kurnool Cuddapah Canal Major Irrigation Project |
2 | Irrigation Project Name Alias | |
3 | Purpose | Irrigation |
4 | Type | Major |
5 | Engineering Type | Diversion |
6 | Status | Completed |
7 | State | Andhra Pradesh |
8 | Districts Benefited | Y.s.r.,Mahbubnagar,Kurnool |
9 | Basin | Krishna, Pennar |
10 | River | |
11 | Project Sharing | None |
12 | Intercountry | None |
13 | Interbasin | Yes |
14 | Work Started in 5 Year Plan | Pre-Plan |
15 | Completed in 5 Year Plan | Pre-Plan |
16 | Project Approval Status | |
17 | Year of Approval by Planning Commission | |
18 | Approved Cost (Rs. in cr) | |
19 | Actual Cost (Rs. in cr) | 7.65 |
20 | Culturable Command Area (CCA) (th ha) | 146 |
21 | Ultimate Irrigation Potential (UIP) (th ha) | 112.505 |
22 | Potential Created (PC) (th ha) | 112.505 |
23 | Project Covered under ERM Scheme | Yes |
24 | Project Covered under CADA Scheme | Yes |
25 | Project Covered under AIBP Scheme | No |
26 | Studies Conducted | |
27 | Project Covered under Tribal Sub-Plan | |
28 | Project Covered under Drought Prone Area Programme (DPAP) | |
29 | Remarks | interbasin transfer from Krishna to Pennar Basin. Get regulated releases from Tungabhadara dam/reservoir. During first plan modernisation of project is also carried out. |
# | Name | Type |
---|---|---|
1 | Adinimmayapalli Anicut | Barrage/ Weir/ Anicut (BWA) |
2 | PS-0 (At Muchumarri) | Lift |
3 | Rajouli Anicut | Barrage/ Weir/ Anicut (BWA) |
4 | Santajutur Anicut | Barrage/ Weir/ Anicut (BWA) |
5 | Sunkesula Barrage | Barrage/ Weir/ Anicut (BWA) |