Krishna Koyna Lift Irrigation Project JI00498

« Go Back

#AttributeValue
1Irrigation Project Name Krishna Koyna Lift Irrigation Project
2Irrigation Project Name Alias
3Purpose Irrigation
4Type Major
5Engineering Type Diversion, Lift, Storage
6Status Ongoing
7State Maharashtra
8Districts Benefited Sangli,Belgaum
9Basin Krishna
10River Koyna
11Project Sharing None
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan VI-Plan
15Completed in 5 Year Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 2009
18Approved Cost (Rs. in cr) 2224.76
19Actual Cost (Rs. in cr)
20Culturable Command Area (CCA) (th ha) 172.47
21Ultimate Irrigation Potential (UIP) (th ha) 117.33
22Potential Created (PC) (th ha)
23Project Covered under ERM Scheme No
24Project Covered under CADA Scheme No
25Project Covered under AIBP Scheme Yes
26Studies Conducted
27Project Covered under Tribal Sub-Plan
28Project Covered under Drought Prone Area Programme (DPAP) Yes
29Remarks

Project in brief

The Krishna Koyna Major Lift Irrigation Project is situated in the Krishna basin in Maharashtra State. The project envisages construction of two components namely, Takari part & Mhaisal part.

a) Takari part consists of constructing head works like pump house, manifold, rising main, delivery chamber & allied works etc. for lifting of water from Satapewadi Barrage on Krishna river near Takari of Walwa taluka in Sangli district stage I to IV. It is proposed to utilize 9.29 TMC of water through canal having total length of 188 kms to irrigate 28939 ha. area in Kadegaon, Palus, Walvakhanapur and Tasgaon Talukas in Sangli district.

b) Mhaisal part consists of constructing head works like pump house, manifold, rising main, delivery chamber & allied works etc. in stage I to VI-A & VI-B. It is proposed to utilize 17.36 TMC of water through canals having total length of 373 kms to irrigate 92317 ha. area in Miraj, Kavthemahankal, Tasgaon and Jat Talukas in Sangli district as well as Sangola and Mangalwedha talikas in Solapur District.

c) About 99.4% of command area of this project lies in DPAP area.

d) The Krishna Koyna Major Irrigation Project has been approved by the Planning Commission, Govt. of India in October, 2009 for an estimated cost of Rs.2224.76 crore at 2005-06 price level. The CCA of the project is 1,72,470 hectare and Ultimate irrigation potential is 1,21,250 hectare.

The construction work of the project was started in the year 1984.The Krishna Koyna Major Irrigation Project has been included in AIBP during 2009-10. Upto February 2012 irrigation potential of 9443 hectare is created.