Jirgo Medium Irrigation Project JI01808

« Go Back

#AttributeValue
1Irrigation Project Name Jirgo Medium Irrigation Project
2Irrigation Project Name Alias Jirgo Dam
3Purpose Irrigation
4Type Medium
5Engineering Type Storage
6Status Completed
7State Uttar Pradesh
8Districts Benefited Mirzapur
9Basin Ganga
10River JIRGO
11Project Sharing None
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan II-Plan
15Completed in 5 Year Plan II-Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 1957
18Approved Cost (Rs. in cr) 1.26
19Actual Cost (Rs. in cr) 1.25
20Culturable Command Area (CCA) (th ha) 13.143
21Ultimate Irrigation Potential (UIP) (th ha) 15.9
22Potential Created (PC) (th ha) 15.9
23Project Covered under ERM Scheme No
24Project Covered under CADA Scheme No
25Project Covered under AIBP Scheme No
26Studies Conducted
27Project Covered under Tribal Sub-Plan
28Project Covered under Drought Prone Area Programme (DPAP)
29Remarks
#NameType
1Jirgo DamDam


Print/export
QR Code
QR Code jirgo_medium_irrigation_project_ji01808 (generated for current page)