# | Attribute | Value |
1 | Irrigation Project Name | Handri Neeva Sujala Sravanti (HNSS) Major Irrigation Project |
2 | Irrigation Project Name Alias | |
3 | Purpose | Irrigation |
4 | Type | Major |
5 | Engineering Type | Lift |
6 | Status | Ongoing |
7 | State | Andhra Pradesh |
8 | Districts Benefited | Anantapur,Y.s.r.,Chittoor,Kurnool |
9 | Basin | Krishna, Pennar, East flowing rivers between Pennar and Kanyakumari |
10 | River | Krishna |
11 | Project Sharing | None |
12 | Intercountry | None |
13 | Interbasin | Yes |
14 | Work Started in 5 Year Plan | |
15 | Completed in 5 Year Plan | |
16 | Project Approval Status | Unapproved |
17 | Year of Approval by Planning Commission | |
18 | Approved Cost (Rs. in cr) | |
19 | Actual Cost (Rs. in cr) | |
20 | Culturable Command Area (CCA) (th ha) | 243.8 |
21 | Ultimate Irrigation Potential (UIP) (th ha) | 243.8 |
22 | Potential Created (PC) (th ha) | |
23 | Project Covered under ERM Scheme | No |
24 | Project Covered under CADA Scheme | No |
25 | Project Covered under AIBP Scheme | No |
26 | Studies Conducted | |
27 | Project Covered under Tribal Sub-Plan | |
28 | Project Covered under Drought Prone Area Programme (DPAP) | |
29 | Remarks | |