Gohira Medium Irrigation Project JI02425

« Go Back

#AttributeValue
1Irrigation Project Name Gohira Medium Irrigation Project
2Irrigation Project Name Alias
3Purpose Irrigation
4Type Medium
5Engineering Type Storage
6Status Completed
7State Odisha
8Districts Benefited Debagarh
9Basin Brahmani and Baitarni
10River Gohira
11Project Sharing None
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan V-Plan
15Completed in 5 Year Plan VII-Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 1975
18Approved Cost (Rs. in cr) 4.795
19Actual Cost (Rs. in cr) 35
20Culturable Command Area (CCA) (th ha) 8.17
21Ultimate Irrigation Potential (UIP) (th ha) 13.8
22Potential Created (PC) (th ha) 13.8
23Project Covered under ERM Scheme No
24Project Covered under CADA Scheme Yes
25Project Covered under AIBP Scheme No
26Studies Conducted
27Project Covered under Tribal Sub-Plan Yes
28Project Covered under Drought Prone Area Programme (DPAP)
29Remarks
#NameType
1Gohira DamDam


Print/export