#AttributeValue
1Irrigation Project Name Eastern Canal Major Irrigation Project
2Irrigation Project Name Alias
3Purpose Irrigation
4Type Major
5Engineering Type Diversion
6Status Completed
7State Punjab
8Districts Benefited Faridkot,Muktsar,Firozpur
9Basin Indus up to International Border
10River Sutlej, Beas
11Project Sharing None
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan Pre-Plan
15Completed in 5 Year Plan Pre-Plan
16Project Approval Status
17Year of Approval by Planning Commission
18Approved Cost (Rs. in cr)
19Actual Cost (Rs. in cr) 8.38
20Culturable Command Area (CCA) (th ha) 216
21Ultimate Irrigation Potential (UIP) (th ha) 97
22Potential Created (PC) (th ha) 97
23Project Covered under ERM Scheme No
24Project Covered under CADA Scheme Yes
25Project Covered under AIBP Scheme No
26Studies Conducted
27Project Covered under Tribal Sub-Plan
28Project Covered under Drought Prone Area Programme (DPAP)
29Remarks Earlier from Ferozpur headworks but now gets water
supply from harike barrage through ferozpur feeder
#NameType
1Ferozepur BarrageBarrage/ Weir/ Anicut (BWA)
2Harike BarrageBarrage/ Weir/ Anicut (BWA)