Diversion Weir of Shahnahar JI03047

« Go Back

#AttributeValue
1Irrigation Project Name Diversion Weir of Shahnahar
2Irrigation Project Name Alias
3Purpose Irrigation
4Type Medium
5Engineering Type Diversion
6Status Completed
7State Punjab
8Districts Benefited
9Basin Indus up to International Border
10River Beas
11Project Sharing None
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan VI-Plan
15Completed in 5 Year Plan VII-Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 1975
18Approved Cost (Rs. in cr) 11.59
19Actual Cost (Rs. in cr) 35.22
20Culturable Command Area (CCA) (th ha)
21Ultimate Irrigation Potential (UIP) (th ha)
22Potential Created (PC) (th ha)
23Project Covered under ERM Scheme No
24Project Covered under CADA Scheme No
25Project Covered under AIBP Scheme No
26Studies Conducted
27Project Covered under Tribal Sub-Plan
28Project Covered under Drought Prone Area Programme (DPAP)
29Remarks