# | Attribute | Value |
1 | Irrigation Project Name | Chambal Major Irrigation Project_Rajasthan |
2 | Irrigation Project Name Alias | |
3 | Purpose | Irrigation |
4 | Type | Major |
5 | Engineering Type | Diversion, Storage |
6 | Status | Completed |
7 | State | Rajasthan |
8 | Districts Benefited | Kota,Sawai Madhopur,Bundi,Baran |
9 | Basin | Ganga |
10 | River | Chambal |
11 | Project Sharing | Interstate |
12 | Intercountry | None |
13 | Interbasin | No |
14 | Work Started in 5 Year Plan | I-Plan |
15 | Completed in 5 Year Plan | III-Plan |
16 | Project Approval Status | Planning Commission |
17 | Year of Approval by Planning Commission | 1952 |
18 | Approved Cost (Rs. in cr) | |
19 | Actual Cost (Rs. in cr) | 18.72 |
20 | Culturable Command Area (CCA) (th ha) | 229.86 |
21 | Ultimate Irrigation Potential (UIP) (th ha) | 213 |
22 | Potential Created (PC) (th ha) | 213 |
23 | Project Covered under ERM Scheme | No |
24 | Project Covered under CADA Scheme | Yes |
25 | Project Covered under AIBP Scheme | No |
26 | Studies Conducted | |
27 | Project Covered under Tribal Sub-Plan | No |
28 | Project Covered under Drought Prone Area Programme (DPAP) | |
29 | Remarks | |