Banganga Canal Major Irrigation Project JI01916

« Go Back

#↓Attribute↓Value↓
1Irrigation Project Name Banganga Canal Medium Irrigation Project
2Irrigation Project Name Alias
3Purpose Irrigation
4Type Medium
5Engineering Type Diversion
6Status Completed
7State Uttar Pradesh
8Districts Benefited Siddharth Nagar
9Basin Ganga
10River Banganga
11Project Sharing None
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan I-Plan
15Completed in 5 Year Plan II-Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 1953
18Approved Cost (Rs. in cr) .24
19Actual Cost (Rs. in cr) .45
20Culturable Command Area (CCA) (th ha) 17.825
21Ultimate Irrigation Potential (UIP) (th ha) 6.239
22Potential Created (PC) (th ha) 6.239
23Project Covered under ERM Scheme No
24Project Covered under CADA Scheme No
25Project Covered under AIBP Scheme Yes
26Studies Conducted
27Project Covered under Tribal Sub-Plan
28Project Covered under Drought Prone Area Programme (DPAP)
29Remarks
#↓Name↓Type↓
1Banganga BarrageBarrage/ Weir/ Anicut (BWA)


Print/export
QR Code
QR Code banganga_canal_major_irrigation_project_ji01916 (generated for current page)