Ballar Medium Irrigation Project JI02819

« Go Back

#AttributeValue
1Irrigation Project Name Ballar Medium Irrigation Project
2Irrigation Project Name Alias Belar, Balar
3Purpose Irrigation
4Type Medium
5Engineering Type Diversion, Storage
6Status Completed
7State Chhattisgarh
8Districts Benefited Raipur
9Basin Mahanadi
10River Balar Nalla
11Project Sharing None
12Intercountry None
13Interbasin No
14Work Started in 5 Year Plan V-Plan
15Completed in 5 Year Plan IX-Plan
16Project Approval Status Planning Commission
17Year of Approval by Planning Commission 1977
18Approved Cost (Rs. in cr) 2.67
19Actual Cost (Rs. in cr) 11.73
20Culturable Command Area (CCA) (th ha) 5.58
21Ultimate Irrigation Potential (UIP) (th ha) 5.57
22Potential Created (PC) (th ha) 5.57
23Project Covered under ERM Scheme No
24Project Covered under CADA Scheme Yes
25Project Covered under AIBP Scheme No
26Studies Conducted
27Project Covered under Tribal Sub-Plan Yes
28Project Covered under Drought Prone Area Programme (DPAP)