Balh Valley Left Bank Medium Irrigation Project JI01708
# | Attribute | Value |
---|---|---|
1 | Irrigation Project Name | Balh Valley Left Bank Medium Irrigation Project |
2 | Irrigation Project Name Alias | |
3 | Purpose | Irrigation |
4 | Type | Medium |
5 | Engineering Type | Lift, Storage |
6 | Status | Ongoing |
7 | State | Himachal Pradesh |
8 | Districts Benefited | Mandi |
9 | Basin | Indus up to International Border |
10 | River | Beas |
11 | Project Sharing | None |
12 | Intercountry | None |
13 | Interbasin | No |
14 | Work Started in 5 Year Plan | VI-Plan |
15 | Completed in 5 Year Plan | |
16 | Project Approval Status | Planning Commission |
17 | Year of Approval by Planning Commission | 2005 |
18 | Approved Cost (Rs. in cr) | 41.64 |
19 | Actual Cost (Rs. in cr) | |
20 | Culturable Command Area (CCA) (th ha) | 2.78 |
21 | Ultimate Irrigation Potential (UIP) (th ha) | 4.35 |
22 | Potential Created (PC) (th ha) | |
23 | Project Covered under ERM Scheme | No |
24 | Project Covered under CADA Scheme | Yes |
25 | Project Covered under AIBP Scheme | Yes |
26 | Studies Conducted | |
27 | Project Covered under Tribal Sub-Plan | No |
28 | Project Covered under Drought Prone Area Programme (DPAP) | |
29 | Remarks | From Sunder nagar balalcing reservoir through syphon |
# | Name | Type |
---|---|---|
1 | Balh Lift Station - I | Lift |
2 | Pandoh Dam | Dam |